Construction and workmanship defects
Is a deadline running? Call us: +41 44 502 91 60
We support property owners and clients with defects in new buildings, conversions and tradesmen’s work. We review the contract, deadlines and defect rights and enforce legitimate claims against contractors and sellers.

Contract for work, acceptance and defects
Anyone who has a house built, a flat converted or work carried out by tradesmen generally concludes a contract for work under Art. 363 et seq. OR. The contractor owes a work free from defects. A defect exists where the work deviates from the contract, that is, where an agreed or presupposed characteristic is missing.
After delivery, the client must inspect the work and give notice of defects (Art. 367 OR). SIA Standard 118 is often agreed in addition; it contains its own rules on acceptance, notice periods and guarantee periods. The specific contract is therefore always the starting point.
Notice periods and the law in force since 2026
For contracts concluded since 1 January 2026, a notice period of 60 days applies to immovable works. It runs from delivery for apparent defects and from discovery for hidden defects (Art. 367 para. 1bis and Art. 370 para. 4 OR). This period may not be shortened by contract. The same period applies to the purchase of land (Art. 219a OR).
Older contracts remain subject to the previous law, which requires immediate notice. Late notice puts defect rights at risk. Record when you discovered the defect and give notice in writing and in a way you can prove.
Defect rights and limitation
Depending on the situation, the client may demand rectification, a reduction of the price or, for serious defects, rescission; where the contractor is at fault, damages may be added (Art. 368 OR). Since 2026 the right to rectification free of charge can no longer be excluded by contract for buildings (Art. 368 para. 2bis OR).
Claims for defects in an immovable work become time-barred five years after acceptance (Art. 371 para. 2 OR). Since 2026 this period can no longer be shortened. Irrespective of this, a defect that has been discovered must be notified in time.
Frequently asked questions
How long do I have to give notice of a construction defect?
For contracts concluded since 1 January 2026, the notice period for immovable works is 60 days from delivery or, for hidden defects, from discovery. For older contracts, notice must be given immediately unless agreed otherwise. Where SIA Standard 118 has been agreed, its rules apply in addition.
Can the contractor exclude rectification in the contract?
For buildings this has no longer been possible since 2026: the right to rectification free of charge is mandatory for clients. The same applies to buyers of new buildings that are yet to be built or were built less than two years before the sale (Art. 219a para. 2 OR). Contracts concluded earlier remain subject to the previous law.
When do claims for construction defects become time-barred?
Five years after acceptance of the work. Since 2026 this period can no longer be shortened by contract. Longer periods apply to defects that were deliberately concealed.
What applies if I bought a flat off-plan?
Since 2026 the buyer of a new building has a mandatory right to rectification against the seller, and the notice period is 60 days. In older contracts, defect rights against the seller were often excluded and replaced by assigned claims against the tradesmen. In that case the contract must be reviewed closely.
How do I give proper notice of a defect?
In writing and precisely enough for the contractor to understand what is being objected to: describe where the defect is and how it appears, and state that you hold the contractor responsible. Photographs help. Send the notice in a way that lets you prove its content and date, for example by registered post.
May I have the defect repaired by someone else and claim the costs?
Only after you have set the contractor a reasonable deadline for rectification and it has expired unused. You may then have the work carried out by a third party at the contractor’s expense (Art. 368 para. 2 in conjunction with Art. 366 para. 2 OR). Having repairs done too early puts your claims at risk and makes proof more difficult.
Complex questions from practice
The defect only appears years after moving in. Can I still assert it?
Yes, as long as the limitation period of five years from acceptance is running (Art. 371 para. 2 OR). Hidden defects must, however, be notified after discovery: within 60 days for contracts concluded since 1 January 2026 (Art. 370 para. 4 OR), and immediately for older contracts. A defect is discovered once you are able to recognise its significance and extent.
Record when and how you noticed the defect and give notice early as a precaution. If the limitation period is about to expire, a step is needed to interrupt or suspend it, such as debt enforcement proceedings, a court action or a written waiver by the contractor. Negotiations alone do not stop the period from running.
The contractor, architect and subcontractor blame each other. Whom do I turn to?
Your contractual partners. The contractor is liable to you for the work it owes, even if subcontractors or suppliers made the mistake (Art. 101 OR). The architect or engineer is liable for planning and site-management errors under their own contract. If it is unclear where the cause lies, give notice to everyone who may be responsible.
An expert report is often needed to establish the cause and allocate responsibility. A joint inspection with a written record is useful; if no agreement is reached, the court can order the precautionary taking of evidence. How those involved share the loss among themselves is their concern and must not delay your claims.
The purchase contract says the seller assigns me the defect rights against the tradespeople and is not liable itself. Is that valid?
Such clauses were common in off-plan purchases. For contracts concluded since 1 January 2026, the buyer of a building that is still to be constructed or was newly built less than two years before the sale may demand rectification free of charge from the seller (Art. 219a para. 2 OR). For buildings, this claim cannot be excluded in advance (Art. 368 para. 2bis OR).
For older contracts, the exact wording matters. An exclusion does not apply to defects that were fraudulently concealed (Art. 199 OR), and the assignment only helps to the extent that the assigned rights exist and are not time-barred. Have the contract and deadlines reviewed before taking action against the seller or the tradespeople.
May I withhold the final payment because of a defect?
As long as the contractor has not remedied a defect you have notified, you may withhold part of the price. The amount should be reasonably proportionate to the expected cost of rectification. Withholding too much puts you in default yourself and exposes you to default interest or a building contractor’s lien.
State in writing why and how much you are withholding and refer to your notice of defects. If SIA Standard 118 has been agreed, its rules on retention and security apply. In the case of condominium ownership, it must also be clarified who asserts defects in the common parts.