General and total contractors

We advise general and total contractors as well as clients and subcontractors on drafting and performing general and total contractor agreements. We review price and deadline provisions, securities and liability along the contractual chain.

Cranes above a building under construction

General contractor and total contractor

A general contractor undertakes towards the client to carry out the entire construction of a building and awards parts of it to subcontractors. A total contractor additionally takes on the planning. In both cases the client has a single contractual partner; the agreement is generally treated as a contract for work under Art. 363 et seq. OR.

There is no contract between the client and the subcontractors. The general or total contractor answers for their work (Art. 101 OR) and has to coordinate deadlines, quality and payments along the entire contractual chain.

Price, deadlines and change orders

A lump-sum or global price is often agreed. With a fixed price the contractor in principle bears the risk of additional effort itself; only extraordinary circumstances that could not be foreseen can justify an adjustment (Art. 373 OR).

Disputes often arise over change orders, additional costs and delay. Clear rules on change management, deadlines, contractual penalties and the payment schedule help prevent them. Where SIA Standard 118 has been agreed, its notification and form requirements must be observed.

Liability for defects, securities and liens

The general or total contractor is liable to the client for the entire work. Since 2026 the 60-day notice period and the mandatory right to rectification apply to buildings. Contracts with subcontractors should be drafted so that recourse does not fail because of shorter periods.

If the general contractor does not pay its subcontractors, they may have a builders’ lien registered on the client’s property. Clients protect themselves with payment schedules, proof of payment or performance guarantees, contractors with instalment payments and security for their remuneration.

Frequently asked questions

How do general and total contractors differ?

A general contractor carries out a project that the client has developed with its own planners. A total contractor plans and builds. With a total contractor, responsibility for planning errors therefore also lies with a single contractual partner.

Does the client have to pay if the general contractor does not pay its subcontractors?

There is a contract only with the general contractor. The subcontractors may, however, demand a builders’ lien on the property. The client then risks paying twice for the same work unless it has protected itself.

Can a lump-sum price be increased afterwards?

Only exceptionally. Additional costs from the client’s change orders must be paid if they were notified in accordance with the contract. For other additional costs the law requires extraordinary circumstances that were not foreseeable or were excluded by the assumptions of both parties.

What role does SIA Standard 118 play?

It applies only where it has been agreed and governs acceptance, remuneration, change orders and liability for defects in detail. Mandatory statutory law takes precedence. For contracts since 2026 this mainly concerns the notice period and the right to rectification.

Who is liable for planning errors?

Under a design-and-build contract, the design-and-build contractor, because it owes both planning and execution. Under a general contractor agreement, the plans come from the client or its planners; the general contractor must nevertheless point out recognisable errors. If it fails to do so, it shares liability.

Can the client terminate the contract early?

Yes. As long as the work is not completed, the client may withdraw at any time but must pay for the work done and fully indemnify the contractor (Art. 377 OR). In the event of delay or foreseeably defective performance, special rights exist without this duty to indemnify (Art. 366 OR). Contracts often regulate the consequences of termination differently.

Complex questions from practice

The client keeps ordering changes during construction but refuses to adjust the lump-sum price. What applies?

The lump-sum price covers the work originally agreed (Art. 373 para. 1 OR). Variations are additional or modified services and must in principle be paid for separately. Disputes usually concern whether a service was already owed and whether the change was ordered in the form required by the contract.

Record every change in writing before it is carried out, including its effect on price and deadlines. If the contract or SIA Standard 118 prescribes a particular form or notification, you should comply with it; anyone who performs more without an order bears the risk. A precise specification is the basis for distinguishing additional from reduced services.

A subcontractor threatens a building contractor’s lien although the client has paid us. How do we respond?

The subcontractor’s claim exists regardless of whether the client has paid the general contractor (Art. 837 para. 1 no. 3 ZGB). If the lien is registered, the client will turn to you. Clarify quickly whether the claim is justified and the four-month period has been observed.

Registration can be averted by providing adequate security, for example a bank guarantee; it must cover the claim and default interest for ten years (Art. 839 para. 3 ZGB). If the claim is disputed, it is decided in the proceedings for definitive registration. Set out in your contracts who provides the security in such cases.

Construction is delayed because of late plans from the client and supply shortages. Do we have to pay the contractual penalty?

A contractual penalty for delay generally requires that you are responsible for the delay. Delays from the client’s side, such as late plans or decisions, give rise to a claim for an extension of time. In the case of supply shortages, it depends on who bears the procurement risk under the contract.

Give written notice of hindrances immediately and request an adjustment of the deadlines; many contracts and SIA Standard 118 make the extension conditional on this. Keep a site diary that documents causes and duration. The court may reduce an excessively high contractual penalty (Art. 163 para. 3 OR).

The general contractor runs into payment difficulties. What can the client and subcontractors do?

The client should link payments to construction progress and require proof that subcontractors have been paid; otherwise there is a risk of paying twice through building contractors’ liens. Contractual securities such as performance guarantees or direct-payment rights must be called in good time. Subcontractors must keep the four-month period for the lien in view (Art. 839 para. 2 ZGB).

If the general contractor goes bankrupt, the bankruptcy administration decides whether to take over the contract. Outstanding claims must be filed in the bankruptcy. Acting early leaves more options: securities granted only shortly before bankruptcy may be open to challenge.