Builders’ lien

Is a deadline running? Call us: +41 44 502 91 60

We support tradesmen, construction companies and subcontractors in securing their remuneration through the statutory builders’ lien. We also advise property owners and general contractors on defending against and replacing liens.

Construction site with a barrier in front of a building shell in Zurich

Who can demand the lien

Tradesmen and contractors who have supplied materials and labour, or labour alone, for buildings or other works on a property are entitled to a statutory mortgage (Art. 837 para. 1 no. 3 ZGB). This also covers demolition work, scaffolding and the securing of excavation pits.

Subcontractors without a contract with the property owner are also entitled. The claim is directed against whoever owns the property at the time. It cannot be waived in advance (Art. 837 para. 3 ZGB).

Four-month period and provisional registration

The lien must be entered in the land register no later than four months after completion of the work (Art. 839 para. 2 ZGB). Filing the application within this period is not enough. If the deadline is missed, the claim is forfeited.

In practice a provisional registration is therefore requested from the court, in urgent cases without hearing the other party. The claim, the work and compliance with the deadline must be shown to be credible. An action for definitive registration must then be brought within the period set by the court.

Defence and replacement by security

The owner can avert registration by providing adequate security for the claim, for example a bank guarantee or a deposit. Since 1 January 2026, security covering the claim and default interest for ten years is sufficient (Art. 839 para. 3 ZGB).

Clients face the risk of paying twice: if the general contractor has not paid its subcontractors, they can still encumber the property. Payment schedules, proof of payment and guarantees reduce this risk.

Frequently asked questions

When does the four-month period begin?

On completion of the work. The last work forming part of the contractually owed performance is decisive. Minor ancillary work or the remedying of defects does not generally trigger a new period.

Can I demand a lien as a subcontractor?

Yes. The claim does not require a contract with the property owner. It exists even if the owner has already paid the general contractor.

What can the owner do against a provisional registration?

The owner can dispute the claim or compliance with the deadline, or provide adequate security. In the subsequent proceedings for definitive registration the contractor must prove its claim.

Which services do not give rise to a lien?

Pure deliveries of materials without labour for the specific building and planning services by architects and engineers are generally not covered. The distinction must be assessed in the individual case.

How high is the secured amount?

It corresponds to the outstanding claim for labour and materials provided for the specific property, plus default interest. Damages or contractual penalties, for example, are not covered. Where several properties are involved, the claim must be divided among the individual properties.

What does a mistake with the deadline cost?

The entire right to the lien. If it is not entered in the land register within four months of completion of the work, it is forfeited (Art. 839 para. 2 ZGB). The claim itself remains but is then no longer secured by the property.

Complex questions from practice

Do remedial works and minor finishing works count for the start of the four-month period?

The decisive point is completion of the work (Art. 839 para. 2 ZGB). This includes the works that form part of what is owed under the contract. According to case law, minor ancillary works, mere touch-ups and warranty works generally do not postpone the start of the period.

Relying on late minor works risks losing the lien. Calculate cautiously from the day on which the work was essentially finished and document the last works with work reports. Where there are several contracts or stages, the period may run separately for each service.

The building has been divided into condominium units or has since been sold. Where and against whom is the lien registered?

The lien is directed against the current owner of the property, even if they acquired it only after the works. Where condominium ownership has been established, the individual units must be encumbered and the secured amount divided among the units. A collective lien on all units for the entire claim is in principle not permitted.

This requires a precise allocation of the services and takes time. Check the current land register entries early and start the allocation before the deadline becomes pressing. Errors in designating the properties or the owners often cannot be corrected once the period has expired.

The owner has already paid the general contractor in full. Can the owner resist the subcontractor’s lien?

Not by pleading payment: the subcontractor’s claim exists even if the owner has paid its own contractual partner (Art. 837 para. 1 no. 3 ZGB). The owner may, however, dispute the claim, the eligibility of the services for a lien and compliance with the deadline, or provide adequate security (Art. 839 para. 3 ZGB).

If the owner has to satisfy the subcontractor, it has recourse against the general contractor; this is of little help if the latter is insolvent. Preventive measures are payments according to construction progress against proof that subcontractors have been paid, and guarantees. Anyone buying a property with ongoing or recently completed construction work should address this risk in the purchase contract.

The court has granted the provisional entry. What happens next?

The provisional entry secures the ranking but does not decide the claim (Art. 961 ZGB). The court sets a deadline for the action for definitive registration. If it is missed, the provisional entry lapses, and by then the four-month period has usually long expired.

In the main proceedings, the claim, the eligibility for a lien and compliance with the deadline must be proven; showing them to be plausible is no longer sufficient. At this stage, security is often provided and the lien deleted, so that only the claim remains in dispute. Check whether the action for payment against the customer can be combined with the proceedings.